Substation Engineering Project Highlights Collaboration

When a wind power generation company approached Western Farmers Electric Cooperative (WFEC) to tie into their system, WFEC faced an immediate challenge—the nearest substation was already at capacity.
WFEC turned to SEL to engineer and manage the construction of a new switching station. The project highlighted the advantages of deploying flexible substation engineering solutions, which enabled progress despite COVID-19 supply chain disruptions.
Discover how WFEC and SEL successfully brought the wind farm online—on schedule and without disruption.